MRA launches Solar power system

by PNG Business News - October 21, 2022

Photo: Chairman of MRA board Mr Benny Kimisive cutting the ribbon to officially commission the solar project. Present is OIC Mr Nathan Mosusu and from PPL Mr Roy Daggy.

The Mineral Resources Authority (MRA) will save about 60 percent of its annual energy bills averaging about K650, 000, with the launching of its new Photo-Voltaic (PV) solar power system.

The PV solar power system was launched today at the Mining Haus by the Chairman of the MRA Board, Mr. Benny Kimisive and Officer-In-Charge (OIC) Nathan Mosusu.

The grid-tie system installed on the roof-top of the Mining Haus has a capacity of 162 Kilo Watt. It will be used as a power source which will operate concurrently with the PNG Power Limited (PPL) grid, to supply the building’s power demand of about 250 KW. The system is designed to operate at optimum with the balance of the building’s power demand to be supplied by the PPL utility grid. This will have a great effect on the final electricity bills.

The project has been installed in partnership with PNG Power Limited (PPL). It is part of PPL’s project called the ‘Roof-top solar photovoltaic pilot project.

Mr Mosusu while officiating at the event, said the project is a demonstration of the MRA’s commitment towards achieving the government’s national strategic development plan of generating 25 percent of electricity from renewable resources by 2030.

He said we had been relying on fossil fuel for electricity and that this was the beginning of a paradigm shift towards doing things smarter using greener technology, and solar energy is a step in the right direction.

Mr. Mosusu said in 2018 alone, PNG imported about 42, 000 barrels of fossil fuel oil, adding that the MRA’s new power source would contribute to the reduction in these statistics. The OIC said the biggest share of the 42, 000 barrels of oil, would no doubt, be attributed to the power requirements of the mining industry. “As the regulator, we at MRA must set the standards in reducing our carbon footprint, so that the industry can hopefully follow suit,” said Mr Mosusu.

Chairman of the MRA Board Benny Kimisive, said that the board had been supportive of this project since inception adding that this would greatly reduce MRA’s power cost. He said there were more of such projects in the pipeline and that the board would continue to support the MRA’s management in achieving these projects.

PNG Power Limited CEO Obed Batia said in a statement that the initiative of Roof-top Solar PV project is part of the organisation’s Pacific Renewable Energy Advisory Project, which is supported by the International Finance Corporation (IFC). Mr Batia said under this project, there were 10 organisations were participating including MRA. He said MRA was the first participant to have successfully installed the system.



Related Articles

Mining

PNG Business News - May 26, 2021

MRA Provides Division on Mine Closures

The Mineral Resources Authority (MRA) will provide a division that will concentrate on what happens when a mine closes. One of the problems found in the industry, according to managing director Jerry Garry, is mine closure. “We are also looking to make sure that there is proper planning or sustainability beyond a mine closure,” he said. “When we close a mine, what else do we have for the people? Do we start growing coffee, cocoa trees to make sure there is economic sustainability beyond the mine? These are the real challenges that we need to address.” According to Garry, the mining industry is organized in such a way that it considers the whole mining life cycle. “In a normal mine life cycle, you would have exploration as the fountain of the business, then you have construction and development, operation of the mine and, eventually, closure,” he said. “These different aspects of the mining business are described in the organisations that are created. And under the MRA, we ensure that the country’s perspective is maintained through marketing and promotion of the mineral assets we have in the country.” Gary also mentioned the importance of exploration investment in the region. “There can never be any mining in the country (without exploration,” he said. “So it is a critical part of the business. We always say that without exploration, there is no money.”   Reference: The National (19 May 2021). “Authority looking at sustainable plans after mine closures”. 

Mining

PNG Business News - July 15, 2021

Stakeholder Support is Needed, Says MRA

The Mineral Resources Authority (MRA) is happy with the conclusion of the recent Consultative Meeting in Wabag, as well as the landowners' demands that the Porgera mine be reopened as soon as feasible. The re-opening of the mine, according to MRA Managing Director Jerry Garry, is contingent on the conclusion of various agreements between Kumul Minerals Holdings Limited, the State, and Barrick Niugini Limited (BNL), which are presently being negotiated by the State Negotiation Team. The leaders of the Porgera mining project's 200 to 300 landowners who attended the conference expressed their wish to reopen the mines. According to the MRA, Kumul Minerals Holdings must apply for Registration of the Dealing and legal transfer of interests in Special Mining Lease 11 to BNL and a new project company with Mineral Resources Enga and Landowners at the conclusion of either the Shareholders Agreement or the Commencement Agreement. He added the Mining Minister's mining advisory committee will decide on the transfer to allow the new project business and its shareholders to manage the mine. Furthermore, Garry stated that several legislative criteria for the issuance of SML under the Mining Act 1992, which have been delayed by the Mining (Amendment) Act 2020, must be met concurrently with the commercial talks. MRA has established a set of minimal but important needs, and its staff will be on the ground to guarantee that all relevant consents and agreements are in place before the mine reopens. Garry further noted that the Mining Act of 1992 imposes conditions on the Development Forum that must be met before the Mining Minister requests position papers, attendance, and involvement for the agreement. He said: “Despite the informal acceptance of submission by several stakeholders, everyone will be formally called upon when the minimum requirements are satisfactorily met through the due processes.” In the next months, the Mineral Resources Authority and the State Team will work diligently to ensure that all minimal criteria are satisfied. The team will be implementing programs on-site in the Porgera mine region, and everyone is urged to participate in those activities that will help the mine reopen. “We are aware of the differences among landowners over leadership issues but their consent and support to the government process is required in the best interest of the project and the nation in our endeavour to re-open the mine. “And at the heights of securing a much better deal for landowners, local level government, the provincial government and the State.”    Reference: Loop PNG (14 July 2021). “MRA Calls For Stakeholder Support”.

Mining

PNG Business News - June 27, 2022

PNGEITI Praises MRA For Digital Platform

The PNG Extractive Industries Transparency Initiative has praised the Mineral Resources Authority's and mine operators' efforts in developing a digital platform that would give real-time mineral data from all of the country's main mines. According to Lucas Alkan, the National Secretary of the PNG Extractive Industries Transparency Initiative (PNGEITI). Live data, according to Mr. Alkan, will contain numbers reflecting production value, export value, and related information, which will be live-streamed from a data source of the respective mine operators. After engineers finish their work, he said, Ok Tedi Mine would be the first to stream live data to the MRA website for public access, and other mines will follow soon after. “The cooperation between the mine regulator and the extractive companies to make live data available for public viewing is an excellent undertaking to garner investor-public trust and confidence in the way the mining industry is regulated and progressing. PNGEITI highly commends these efforts,” Mr. Alkan said. Mr. Alkan stated that PNGEITI applauds the leadership of the Mineral Resources Authority (MRA) under managing director Jerry Garry since this initiative will complement and enhance EITI reporting in the country.   Reference: Poat-Courier (21 June 2022). “Live Mining Data, An Excellent Tool For Transparency”.


Recent Articles

Tourism

PNG Business News - February 05, 2023

PNG Tourism Promotions Authority (TPA) and Bougainville TPA signs MOU

The Department of Commerce, Trade and Industry reached another milestone recently when it signed a Memorandum of Understanding (MoU) with the Papua New Guinea (PNG) Tourism and Promotions Authority (TPA). The MOU paves the way forward for both parties to continue bilateral partnership based on the understanding of tourism and promotions in Bougainville. The MOU was signed by the PNG TPA and the ABG Department of Commerce, Trade and Industry on the understanding relating to a joint partnership for the protection and preservation of tangible and intangible culture, development and promotion of tourism, contemporary culture and the arts and sustainable tourism in the autonomous region of Bougainville. ABG Vice President and Minister for Commerce Trade and Industry, Hon. Patrick Nisira (MHR) acknowledged the PNGTPA for its tremendous support so far since the first MoU was signed in 2016. The support has cemented many agreements already signed and has proven that Bougainville is truly a tourism destination that is worth investing time and money on. Mr. Nisira acknowledged the PNG TPA officers for their continuous negotiation with the Bougainville partners in pushing for significant income generating programmes to proceed in the region. “Standing here today it gives me great pleasure to witness and participate in this significant event that will go down in history books of this nation to be. We are here today to mark this important event on the signing of the MOU between my ministry and the department of national government and PNG Tourism Promotions Authority (PNG TPA).” This agreement adds value to our collective vision, ideas and consultations that the local tourism and cultural practitioners in both government and private sectors, he said. “As a way forward the agreement presents a realistic and workable approach to tourism development and its sustainability in the region.” “The MOU also sets out a framework for future development for tourism emphasizing on effective and determined and holistic approaches.” He said that the agreement generally outlines the pros and cons of tourism development in Bougainville and the framework and strategy of reaching the targeted goals and vision earmarked to reaching the overarching goals of economic building and development.         Deputy Chief Secretary for Operations Anthony Koiri approved and signed the MOU on behalf of the Bougainville Public Service Chief Secretary who is on sick leave at the moment. The signing was witnessed by the staff of the PNG Tourism Promotions Authority (PNGTPA), Department of Commerce, Trade and Industry, senior officers and a small crowd at the Bel Isi park.

Mining

PNG Business News - February 05, 2023

PNGEITI POSITION ON PORGERA MINE LEGACY TAX ISSUES

The PNGEITI Head of Secretariat Mr. Lucas Alkan says all parties to the Pogera Mine must adhere to rules governing the extractive industry, particularly when dealing with fiscal matters that must be administered and observed according to law. His comments follow a news article on The National citing the Internal Revenue Commission (IRC) that unmet tax obligations of the Pogera mine stood in the way to expedite the mine re-opening process.  Mr. Alkan says a workable and timely strategy that does not impinge on basic laws is a way forward.   Below is the full comment on this issue.  “The Papua New Guinea Extractive Industries Transparency Initiative (PNGEITI) commends The National newspaper for attempting to bring to light what appears to be the final outstanding issue (among others) in the Porgera Mine recommencement negotiations (more on this in footnote). We’ve noted from the reporting that taxation matters are legacy issues that appear to be standing in the way for the multi-million-kina Porgera Gold Mine to re-open. We have observed that the Government was on track to conclude negotiations and re-open the Mine by June last year, however this did not eventuate as anticipated. Attempts to reopening the Mine in the second half of last year was not feasible due to the national general elections and the formation of government. It appeared that all negotiations were concluded and a new Porgera Mining Agreement Framework was in place for the Mine to be re-opened in the first quarter of this year. Surprisingly, we learn that an old Porgera Tax liability dispute is standing in the way for the Mine to be re-opened. The early recommencement of the Mine, preferably within the first quarter of this year is critical for the country as the lead time required for mobilizing resources and the significant start-up capital needed to get the mine back into its full operating capacity would be a significant challenge. On this, we are aware there are also discussions going on with the developer and the government as to who is going to meet the startup cost but we understand Barrick Niugini Limited might meet the full cost of starting up the Mine and government would refund later but unsure as to whether this understanding has been reached or not yet. With regards to the current standoff, the EITI based on its global best practice principles is of the view that the existing law governing taxation matters must dictate or take precedence over any political intervention. We do not know the specifics of the on-going tax matter but understand that it is related to a tax dispute concerning the ‘old Porgera Mine’. If it is a significant amount of tax owed by Barrick to the Government based IRC’s audit in 2013 then it is a legal tax obligation that Barrick and its joint venture partners need to settle as required by law. We fail to understand as to why the old Porgera tax obligation/liability clause was inserted into the new Porgera Mining Framework Agreement making it a condition to resolve this legacy tax issue before reopening the Mine. If whatever was reported and commented by PM Marape recently is true then Barrick Niugini Limited and the State need to speed up the negotiation process and resolve this dispute immediately. Both parties should exercise good faith – Barrick Niugini Limited should not pull strings on this old Porgera tax liability matter and delay the re-opening of the Mine. It is understood the State (IRC) may not easily forego if there is a substantial amount of tax liability to be paid by the operator. Whatever the parties decide to do, they should resolve the tax liability issue through the due process of law but allow the Mine to re-open immediately under the New Porgera Framework Agreement. Political intervention is not recommended to resolve this dispute as this can undermine investor confidence, set bad precedence for the Government and create an uneven playing field for project developers. Barrack Niugini Limited should not put undue pressure on the State to resolve this matter politically in order to re-open the mine as it is not a best business practice. All stakeholders and the citizens have the right to know the specific issues or the nature of this tax liability issue between Barrick Niugini Limited (BNL) and the Internal Revenue Commission (IRC) as the continued delay in re-opening the Mine continues to have negative consequences on the economy.  The prolonged delay has not only resulted in significant revenue loss to the Government (including the provincial and local level governments in the impacted resource area) but also loss of employment, business opportunities and spin-off benefits to the landowners and the wider communities. The shutting down of the Mine 3 years ago has had significant negative consequences on the economy including the current foreign exchange shortage that has constrained business operations in the other sectors of the economy. Porgera Mine had been a good source of foreign exchange inflows and its continued shutdown will definitely not going to contribute to the 4% economic growth (that was largely to be driven by the extractive sector) projected for by the World Bank for last year and the real GDP growth of 4% projected for this year in the 2023 National Budget. PNGEITI commends the transparent negotiation process to date that took substantial amount of time and effort to ensure the interests of all parties were reflected in those agreements. We encourage all parties to continue to respect and observe the laws of the land in this dispute resolution process to address the tax liability issue. We believe that a win-win situation for both parties (Government and Barrick) is to re-open the mine first and work together to resolve the outstanding tax liability dispute later going forward.

Company

PNG Business News - February 02, 2023

Weir Minerals releases the 6th edition of the Warman® Slurry Pumping Handbook, the definitive resource for slurry pumps

Photo: The Warman Slurry Pumping Handbook is the definitive guide for most slurry pumping applications. Weir Minerals, manufacturer of the industry-leading Warman®  slurry pump, has released the latest edition of their coveted Warman® Slurry Pumping Handbook. The 6th edition, compiled by the most trusted name in slurry pumps, features detailed engineering data required for most slurry pumping applications. Drawing on decades of Weir Minerals’ inhouse expertise in innovative engineering and slurry pumping technology, the new handbook has updated reference material based on new learnings, improved understanding and technological developments within the mining industry. With customers always in mind, the handbook aims to empower engineers to achieve optimal performance from their Warman® slurry pumps. An increased global focus on the environment, energy consumption and water conservation will influence slurry pump design and considerations – making this latest handbook an essential tool for all current and future pump engineers. “Pumping slurry has many challenges and I’m excited to publish our latest handbook, packed with fundamental theory, application advice, standard practices and latest Warman learnings from the field; all aimed to help our customers, present and future, deliver with excellence.” Marcus Lane, Director, Slurry Pumping Technology Group Weir Minerals are continually striving to shape the next generation of smart, efficient and sustainable solutions with cutting-edge science and innovation. The comprehensive handbook includes over 140 pages of detailed information, including performance charts, impeller design, part configuration, assembly and slurry considerations – fully supported by accurate technical renders and specifications. “The high quality of the reference material in this essential resource reflects the leading status of the Warman slurry pumps. As the industry leader, we have a responsibility to develop our future engineers; we will make the latest version of the Warman Slurry Pumping Handbook available not only to our customers, but also to the leading schools worldwide, so they can learn from the best in the industry.” John McNulty, Vice President Global Engineering & Technology. As part of Weir Minerals’ commitment to investing in STEM education and developing the next generation of engineers, copies of this essential resource will be gifted to the leading mining and engineering educational facilities around the world, including the winner of the 2022 Warman Design & Build competition, Deakin University in Australia.

Join Papua New Guinea's

Business Community

Be the "First" to get our exclusive Digital Magazine & Weekly Newsletter.